Offshore Wind Farms at Akita Port and Noshiro Port
Overall Construction Time Record
Construction Record (Onshore Construction)
Onshore Transmission Lines and Substation at Akita Port
2021/11/17
Restoration construction of main pavement on the underground conduit for electric cables.
To remove temporary pavement and to lay main pavement.
2021/08/31
Completion of construction for onshore step-up substation.
The onshore step-up substation has become operative since September 2, 2021.
2021/08/04
Aluminium container installation work at step-up substation.
To install raised-floor to store cables of control unit for wind power station and substation.
2021/07/13
Equipment installation work at step-up substation.
To install a power receiving device on the completed foundation.
2021/06/17
Equipment installation work at step-up substation.
To install a transformer on the completed foundation.
2021/05/31
Foundation work at step-up substation.
To pour concrete into the area of reinforcing bars and smooth the surface.
MORE
Onshore Transmission Lines and Substation at Noshiro Port
2021/11/20
Restoration construction of main pavement on the underground conduit for electric cables.
To remove temporary pavement and to lay main pavement.
2021/10/05
Completion of construction for onshore step-up substation.
The onshore step-up substation has become operative since October 5, 2021.
2021/09/16
Installation of optical cables at port facility.
To install optical cables which monitor and control wind turbines.
2021/08/26
Cable installation work at step-up substation.
To connect cables transmitting power from wind power station to substation equipment.
2021/07/26
Equipment installation work at step-up substation.
To install a transformer on the completed foundation.
2021/06/29
Foundation work at step-up substation.
To pour concrete into the area of reinforcing bars and smooth the surface.
MORE
Construction Record (Offshore Construction)
Offshore Construction
2022/09/28
Finished the installation of all 33 wind turbines. On September 24, 2022, the installation of the last wind turbine at Akita Port was finished. By this, the installation of all 33 wind turbines consisting of 20 at Noshiro Port and 13 at Akita Port was finished.
2022/07/04
Started Full-scale offshore wind turbine construction. On July 2, 2022, we started full-scale offshore wind turbine construction at Noshiro Port deploying Seajacks Zaratan, a self-propelled SEP (Self-Elevating Platform).
2022/06/15
Seajacks Zaratan has arrived at Akita Port. On June 15, 2022, Seajacks Zaratan, a self-propelled SEP (Self-Elevating Platform), arrived at Akita Port.
2022/04/11
The pre-assembly work of wind turbine towers started. On April 6, 2022, the pre-assembly work of wind turbine towers started at Akita Port.
2022/02/10
The 6th ship has arrived at Akita Port. On February 10, 2022, the 6th ship loaded with 11 towers as wind turbine element arrived at Akita Port.
2022/02/09
The 5th ship has arrived at Akita Port. On February 8, 2022, the 5th ship loaded with 21 blades as wind turbine element arrived at Akita Port.