Onshore Transmission Lines and Substation at Akita Port
2021/11/17
Restoration construction of main pavement on the underground conduit for electric cables.
To remove temporary pavement and to lay main pavement.
2021/08/31
Completion of construction for onshore step-up substation.
The onshore step-up substation has become operative since September 2, 2021.
2021/08/04
Aluminium container installation work at step-up substation.
To install raised-floor to store cables of control unit for wind power station and substation.
2021/07/13
Equipment installation work at step-up substation.
To install a power receiving device on the completed foundation.
2021/06/17
Equipment installation work at step-up substation.
To install a transformer on the completed foundation.
2021/05/31
Foundation work at step-up substation.
To pour concrete into the area of reinforcing bars and smooth the surface.
2021/04/10
Connection of electric cables on Shimoshinjo Tozai Line.
To connect electric cables put through manhole.
2021/04/01
Installation for manhole at step-up substation.
To arrange reinforcement for reinforcing bars.
2021/03/24
Start of installation for electric cables on Shimoshinjo Tozai Line.
To put electric cables through manhole into the underground conduit already buried.
2021/02/19
Installation for underground conduit on Shimoshinjo Tozai Line.
To install underground conduit for electric cables, bury them with sand and crushed stone under the ground and pave the road with asphalt.
2021/01/09
Start of continuity test on Nakano Kasaoka Line.
To check safe entering of electric cables into underground conduit.
2020/12/22
Start of installation for propulsion conduit on non-statutory road.
To dig vertical shaft for propulsion conduit to let conduit for electric cables pass under waterway.
2020/11/02
Start of installation for manhole on Kubo Akita Line.
To install manhole where electric cables are connected.
2020/10/12
Installation for underground conduit on Akita Tennoh Line.
To install underground conduit for electric cables, bury them with sand and crushed stone under the ground and pave the road with asphalt.
2020/09/29
Installation for underground conduit on Shimoshinjo Tozai Line.
To install underground conduit for electric cables, bury them with sand and crushed stone under the ground and pave the road with asphalt.
2020/08/17
Start of installation for manhole on non-statutory road.
To install foundation bottom plate in the excavated hole where manhole is placed.
2020/07/16
Start of construction on Nakano Kasaoka Line.
To install steel plate under the ground to protect against landslide and spring water at the time of excavation.
2020/07/06
Start of installation for underground conduit on non-statutory road.
To install underground conduit for electric cables, bury them with sand and crushed stone under the ground and pave the road with asphalt.
2020/06/29
Start of installation for manhole on Shimoshinjo Tozai Line.
To install manhole where electric cables are connected.
2020/05/08
Start of installation for underground conduit on Shimoshinjo Tozai Line.
To install underground conduit for electric cables, bury them with sand and crushed stone under the ground and pave the road with asphalt.
2020/04/11
Start of construction on Shimoshinjo Tozai Line.
To conduct excavation survey in advance of installing underground conduit for electric cables.