NEWS

Prospect on Start of Commercial Operation

We completed the installation of all 33 wind turbines consisting of 20 at Noshiro Port and 13 at Akita Port before the end of September this year and are carrying out commissioning work of all 33 wind turbines towards the commercial operation.
 
We expect Noshiro Port Offshore Wind Farm where wind turbine installation has preceded to firstly start the commercial operation followed by Akita Port Offshore Wind Farm.
 
While we aim to achieve the commercial operation for both wind farms before the end of this year, it could be delayed until early next year due to continued worse weather than usual or to other reasons considering offshore commissioning work being subject to weather condition.
 
We plan to announce updated prospect on start of commercial operation around late December based on further progress of commissioning work.