NEWS

Started Full-scale offshore foundation construction

On Wednesday 12 May, we started full-scale offshore foundation construction at Noshiro Port by deploying Seajacks Zaratan, a self-propelled SEP (Self-Elevating Platform). A monopile was set at the designated position on Tuesday 11 May, and the hammering was completed on the morning of Wednesday 12 May.
 
By starting this full-scale offshore foundation construction, our construction of an offshore wind farm has reached a turning point. We intend to advance the construction on the principle of safety first.
 
We plan to complete the offshore foundation construction for all 33 units at Akita Port and at Noshiro Port within this year and to start the offshore wind turbine installation from April next year.